Montana Department of Transportation Bridge Underwater Inspections 

 

  • Date: 2018-Present
  • Project Type: Underwater Bridge Inspection

Montana Department of Transportation Bridge Underwater Inspections 

 

  • Date: 2018-Present
  • Project Type: Underwater Bridge Inspection

Key Project Details

  • Underwater inspections of 52 bridges that included scour assessment in accordance with HEC 18
  • Total Trimble Station identified 10 structures that had scour related deficiencies
  • NDT techniques were utilized, which included both timber resistance testing and ultrasonic thickness measurements
  • MicroStation was used to create profile drawings and channel contours

Key Project Details

  • Underwater inspections of 52 bridges that included scour assessment in accordance with HEC 18
  • Total Trimble Station identified 10 structures that had scour related deficiencies
  • NDT techniques were utilized, which included both timber resistance testing and ultrasonic thickness measurements
  • MicroStation was used to create profile drawings and channel contours

Similar Projects

Colorado Department of Transportation Statewide Underwater Inspection of On-System & Off-System Bridges

Divided into 3 task orders: On-System, Off-System, and Blue Mesa
Reservoir bridges.

Wyoming Department of Transportation On-System & Off-System Underwater Bridge Inspections

eO performed 49% of the level I and II underwater inspections.

North Dakota Department of Transportation Underwater Bridge Inspections

Substructures were composed of a variety of concrete, steel, and timber elements.